Sprint planning
Sprint planning is the meeting where a team selects which ready backlog items fit this sprint's capacity and writes the sprint goal.
Planning selects; refinement prepares. Nothing should be written during planning — if an item needs writing, it was not ready and it goes back. That single rule is what keeps a small team's planning to thirty minutes.
The budget is velocity, not enthusiasm. Pulling thirty points on a velocity of twenty because this sprint feels different is the most reliable way to end a sprint demoralised.
In Flocci Projects
The sprint planner drags issues from the backlog into a sprint with points summing live, alongside the velocity trend from completed sprints.
Related terms
See it on a free boardBrowse the whole glossary
- Agile
- Backlog refinement
- Blocker
- Burndown chart
- Burnup chart
- Cycle time
- Daily standup
- Definition of done
- Definition of ready
- Epic
- Kanban
- Lead time
- Planning poker
- Product backlog
- Product owner
- Retrospective
- Scrum
- Scrum master
- Sprint
- Sprint goal
- Sprint review
- Story point
- Swimlane
- Throughput
- User story
- Velocity
- WIP limit