Flocci Projects

HomeHindi-English guides › Sprint planning kaise kare?

Sprint planning kaise kare?

Sprint planning ka simple tarika: pehle pichhle sprints ki velocity dekho, backlog ke top items ko clear karo, un-estimated items pe story points lagao, points ka total velocity tak pahunche tab tak items sprint me daalo, ek line ka sprint goal likho, aur sprint start kar do. Total 30 minute.

Meeting se pehle (10 minute, ek banda)

Ek insaan backlog ko priority ke hisaab se top-down order kare aur dekhe ki upar ke 15 items ka title clear hai aur description itna hai ki estimate ho sake. Agar planning meeting me hi likhna padega to meeting 2 ghante khinchegi — yehi sabse badi galti hai.

Meeting me kya karna hai

1) Velocity chart kholo — pichhle 3 completed sprints ka average hi aapka budget hai. 2) Backlog top-down chalo, jinke points nahi hain unpe estimate lagao. 3) Items sprint me tab tak daalo jab tak points ka total budget tak na pahunche. 4) Sprint goal ek line me likho jo non-technical banda bhi samajh le. 5) Start Sprint dabao.

Do sabse common galtiyan

Pehli: over-commitment — velocity 20 hai aur team 30 points utha leti hai kyunki 'is baar alag hai'. Kabhi alag nahi hota, aur fail hua sprint team ka morale sabse tez todta hai. Doosri: aisa item jise room 2 minute me estimate nahi kar paa raha — wo ready nahi hai, use wapas refinement me bhejo.

Flocci Projects me ye kaise hota hai

Create Sprint me naam, goal, start date aur end date daalte hain. Sprint planner me backlog se issues drag karte jao — points ka total live add hota rehta hai. Completed sprints ki velocity trend bagal me hi dikhti hai. Sprint khatam hone pe Complete Sprint adhoora kaam wapas backlog me bhej deta hai aur charts update ho jaate hain.

Free board banao — card ki zaroorat nahi

Aksar puche jaane wale sawaal

Sprint kitne din ka hona chahiye?

2 hafte standard hai — 1 hafte me estimation ka noise zyada aata hai, 4 hafte me feedback late milta hai. Bahut chhoti team 1 hafta bhi rakh sakti hai. Sabse zaroori baat: length constant rakho, warna velocity compare karne layak nahi rahegi.

Sprint ke beech me urgent kaam aa jaye to?

Swap karo, stack mat karo. Agar urgent item andar aana hi hai to utne hi points ka kaam sprint se bahar nikalo. Jo budget sirf badhta hai wo budget nahi hota.

2 log ki team ko sprint planning chahiye?

Halka version haan. Hafte me 15 minute scope aur goal decide karne me lagao — asli fayda yeh hai ki yahi ek moment hota hai jab aap kisi cheez ko clearly 'na' bolte ho.

Kya Flocci Projects free me sprint planning deta hai?

Haan — personal board bilkul free hai aur usme backlog, sprints, story points aur velocity insights sab included hain. Team ke shared boards ke liye organization banao, seats ₹49 per seat per month.

Aur guides

English versions: agile answers · glossary.