What is planning poker and does it actually work?
The mechanism, not the cards
The physical cards are incidental; the simultaneity is the whole technique. Any method where nobody sees another estimate before committing their own — cards, fingers, a chat message everyone posts on three — captures the same benefit.
The outliers are the point
When one person says 2 and another says 8, each knows something the other does not: hidden complexity, or a simpler approach. That two-minute conversation is the actual product of the session, and the number you write down afterwards is a by-product.
When to stop
One re-vote after discussion, then take the higher number or the mode and move on. Estimation debates that run past a few minutes cost more than the precision they buy, and precision is not what points are for anyway.
Try it on a free Flocci Projects boardRelated questions
Does planning poker work for remote teams?
Yes — everyone types their number and posts simultaneously on a count of three, or uses any tool that hides values until reveal. The requirement is simultaneity, not physical presence.
What if the team always agrees immediately?
That is a good sign for well-understood work, and you can then estimate faster in bulk. Reserve the full ritual for items where the spread is genuinely wide, which is where the conversation pays for itself.
Is AI-suggested estimation a replacement?
No, but it is a decent starting point. Flocci Projects' AI backlog breakdown pre-fills draft point estimates on generated issues, which the team then corrects — that removes the blank page, but the calibration conversation is still where the shared understanding comes from.
More agile answers
- What is sprint velocity and how is it calculated?
- What are story points in agile estimation?
- How do I estimate story points consistently across a team?
- Kanban vs scrum board — which should my team use?
- How do I run sprint planning for a small team?
- What is a product backlog and how do I groom it?
- What is the difference between backlog refinement and sprint planning?
- What are WIP limits in kanban?
- What is the difference between burndown and burnup charts?
- What is an epic in agile project management?
- What is the difference between an epic, a story and a task?
- What is the definition of done in scrum?
- How do I run a daily standup that is not a status meeting?
- What is a sprint retrospective and how do I run one?
- What happens in a sprint review?
- What are the three scrum roles?
- What is the difference between cycle time and lead time?
- What is MoSCoW prioritisation?
- How do I calculate sprint capacity?
- Which agile metrics actually matter for a small team?
- Agile vs waterfall — which is right for my project?